Reclass Process
Use the Reclass API process to change, copy, or replace an existing cost class with a different cost class.
Process Settings
Below are the settings you must define for the Reclass API process.
Setting | Description | Sample Value |
---|---|---|
ProcessID | This setting informs Cobra to run the Reclass process. | Reclass |
Project | This setting refers to the project where you want to run the reclass process.
This setting is required. |
Demo Advanced |
SourceClass | This setting refers to the source class from which you copy, change, or replace the data of the target class.
This setting is required. |
Budget |
SourceAction | Use one of the following values:
|
CopyDelete |
TargetAction | Use one of the following values:
|
Replace |
TargetClass | This setting refers to the target class where you copy, change, or replace data from the source class.
This setting is required. |
OTB |
CopyResourceAssignmentCodeFrom |
Use this setting to specify which class should retain the resource assignment codes. Use one of the following values:
This setting is optional and the default value is the source class. |
Source |
Criteria | Use this setting to choose the selection criterion you want to use for the reclass. The selection criteria change based on the project. Some selection criteria include the following:
This setting is optional and the default value is Total Project. |
Resources |
IncludeChildren | Use this setting to specify whether the selected criterion should include child elements or not.
This setting is optional and the default value is 0. |
1 |
Selection | Use this setting to select the portion of the project for the reclass. The available choices depend on the selections you made in the
Criteria settings.
If you select Total Project for the Criteria setting, the Selection setting is left blank. This setting is optional. By default, no value is specified in this setting. |
1.1 |
Scope | Use one of the following values:
|
DateRange |
StartDateLabel | Use this setting if
Scope=DateRange. This setting refers to a valid calendar label and is the starting date for the
DateRange setting.
This setting is optional and the default value is the starting date for the DateRange setting. |
JAN07 |
EndDateLabel | Use this setting if setting
Scope=DateRange. This setting refers to a valid calendar label and is the ending date for the
DateRange setting.
Use StartDateLabel and EndDateLabel only if you use DateRange for the Scope setting. This setting is optional and the default value is the ending date for the DateRange setting. |
APR07 |
AllowComplete | Use this setting to indicate whether you want to perform a reclass of completed control accounts and work packages or not.
This setting is optional and the default value is the value set in the Allow reclass of completed Control Account and Work Package: option in the Reclass Preferences. |
1 |
IncludeForecastInUpdateTotals | If the target class is a Forecast class, setting this value to
1 will include the Forecast class values when you run the Update Totals process after the Reclass process is finished.
This setting is optional and the default value is 0. |
0 |
CopyBaselineDatesToForecastDates |
If value is set to
1, Cobra copies the baseline dates to the forecast dates if the following conditions are met:
Otherwise, Cobra automatically sets the value to 0. |
1 |
Sample Script
Below is a sample script file for the Reclass API process.
[Process010]
ProcessID=Reclass
Project=Demo Advanced
SourceAction=CopyDelete
SourceClass=Budget
TargetAction=Replace
TargetClass=OTB
Criteria=Resources
IncludeChildren=1
Selection=1.1
Scope=DateRange
StartDateLabel=JAN07
EndDateLabel=APR07
AllowComplete=1
IncludeForecastInUpdateTotals=0
CopyBaselineDatesToForecastDates=1